Clean Crate · SS Engineers & Consultants
Dairy crate washing: measurement plan
Use this evaluation framework to measure an actual project. It is not a published customer case or a claim of achieved savings.
Record the starting point
Count crates received, accepted clean crates, rewash, staff time, shift hours and utility consumption over representative production.
Define a comparable trial
Use similar crate condition and acceptance criteria. Account for warm-up, tank changes and loading constraints; these may not appear in a nominal machine-capacity figure.
Report the outcome
Compare cost per accepted crate and total shift demand. Separate measured results from estimates and document operating conditions. Customer names and performance figures should be shared only with permission.